5/29/20
Work on the correction of the riser tower has begun. Deconstruction of the top of the riser tower, to lower it to the project specifications, is at about 50%. Once the tower has been shortened, the top will again be properly sealed, with a few days of curing afterwards.
After that, the massive riser grate will be re-installed before the lake is re-filled. The contractor hopes to complete the work in about another week from this posting.
Stay tuned here for further updates. Direct all questions to lakes@twinlakeshoa.org.