Lake Shenandoah Restoration

5/29/20

Work on the correction of the riser tower has begun.  Deconstruction of the top of the riser tower, to lower it to the project specifications, is at about 50%. Once the tower has been shortened, the top will again be properly sealed, with a few days of curing afterwards.

After that, the massive riser grate will be re-installed before the lake is re-filled.  The contractor hopes to complete the work in about another week from this posting.

Stay tuned here for further updates.  Direct all questions to lakes@twinlakeshoa.org.